Westcad (Panel 1) 15/03/2015 at 01:50 #70026 | |
MrBitsy
121 posts |
This is now in the process of being transferred to Victoria. All lines blocked south of West Hampstead. Just watched the WestCad signaller make the last move into St.Pancras platform 1 to berth. Monday morning, Kentish town south all lines will be controlled from Three Bridges! TVSC Link 4 signaller - Temple Meads, Bath & Stoke Gifford Log in to reply |
Westcad (Panel 1) 15/03/2015 at 02:14 #70027 | |
BarryM
2158 posts |
I hope all goes well for Monday morning. Barry Barry, Sydney, New South Wales, Australia Log in to reply |
Westcad (Panel 1) 15/03/2015 at 03:29 #70028 | |
kaiwhara
587 posts |
Westcad was an interesting system to use, after using a Westinghouse L Frame for a few years! Let me get this straight though, St Pancras Platforms 1-4 will be controlled by Victoria Eastern? Correct? Sorry guys, I am in the business of making people wait! Log in to reply |
Westcad (Panel 1) 15/03/2015 at 04:07 #70029 | |
John
884 posts |
No, from Three Bridges ROC. This recent document also says Victoria panel 6 is transferring, not sure if it will be at the same time or not. Log in to reply |
Westcad (Panel 1) 15/03/2015 at 04:09 #70030 | |
kaiwhara
587 posts |
" said:No, from Three Bridges ROC.Doh, I meant Three Bridges ROC :doh I hate earlies! Sorry guys, I am in the business of making people wait! Log in to reply |
Westcad (Panel 1) 15/03/2015 at 05:54 #70031 | |
MrBitsy
121 posts |
05:50 and WestCad West Hampstead is no more!
TVSC Link 4 signaller - Temple Meads, Bath & Stoke Gifford Log in to reply |
Westcad (Panel 1) 15/03/2015 at 08:27 #70033 | |
Hpotter
205 posts |
Most of Victoria Eastern Panel 6 is being migrated to Three Bridges ROC, this is from what used to be City Thameslink / Smithfield Sdgs to Elephant & Castle. IIRC Loughborough Jn is staying as part of the NX panel for the time being. Log in to reply The following user said thank you: ozrail |
Westcad (Panel 1) 15/03/2015 at 10:22 #70036 | |
John
884 posts |
Panel 6 is live until 13.00 today, according to the signaller.
Log in to reply |
Westcad (Panel 1) 15/03/2015 at 20:20 #70043 | |
mfcooper
707 posts |
The entirety of "Panel 6" at Victoria, which has been a WestCad workstation for (probably) a couple of years [with a slightly smaller control area compared to the old Panel), and the entirety of the West Hampstead WestCad workstation are migrating to Three Bridges ROC. There will be two people working the combined control area and a meal break signaller per shift. Log in to reply |