South Workstation crossings 18/05/2021 at 15:28 #139593
bugsy
Avatar
1766 posts
There appears to be something that I am misunderstanding.

According to the manual several crossings controlled by the South workstation auto lower. But they don't seem to want to. So what am I doing wrong?
.....


Post has attachments. Log in to view them.
Everything that you make will be useful - providing it's made of chocolate.
Log in to reply
South Workstation crossings 18/05/2021 at 16:04 #139596
headshot119
Avatar
4869 posts
When reporting an issue, please provide save games and not a screen shot, we can't tell anything from a screenshot.
"Passengers for New Lane, should be seated in the rear coach of the train " - Opinions are my own and not those of my employer
Log in to reply
South Workstation crossings 18/05/2021 at 16:07 #139597
jc92
Avatar
3685 posts
I can partially reproduce this with some test trains. trains which approach the crossing with the route already set will trigger Meaford and Aston crossings to lower, however if the route across Meaford after the train has passed beyond SOT260 at Barlaston the crossing auto lower fails to operate. in other words the route has to be set very early. I'm not find this to be a problem with the other listed crossings.

edit: issue occurs after Passing SOT264, not 260

"We don't stop camborne wednesdays"
Last edited: 18/05/2021 at 16:11 by jc92
Reason: None given

Log in to reply
South Workstation crossings 18/05/2021 at 18:48 #139599
bugsy
Avatar
1766 posts
headshot119 in post 139596 said:
When reporting an issue, please provide save games and not a screen shot, we can't tell anything from a screenshot.
Oops, sorry. For some reason I totally forgot. It's happened quite a few times. I've attached a save at 07:10 in which train 1R15 approaches shortly after 07:15.

jc92 in post 139597 said:
I can partially reproduce this with some test trains. trains which approach the crossing with the route already set will trigger Meaford and Aston crossings to lower, however if the route across Meaford after the train has passed beyond SOT260 at Barlaston the crossing auto lower fails to operate. in other words the route has to be set very early. I'm not find this to be a problem with the other listed crossings.

edit: issue occurs after Passing SOT264, not 260
So, are you saying that if I set the route early enough, in either direction, they will lower as per the manual?
I'll give it a try.

Everything that you make will be useful - providing it's made of chocolate.
Log in to reply
South Workstation crossings 19/05/2021 at 13:48 #139619
bugsy
Avatar
1766 posts
The crossings aren't an issue if you set the routes far enough in advance, so all is well.

Hope that I didn't waste too much of anyone's time.

Everything that you make will be useful - providing it's made of chocolate.