Stafford/Norton Bridge 30/03/2016 at 11:18 #81498 | |
HST125Scorton
1198 posts |
So over the Easter weekend the WCML between Crewe Bas Hall Jn to Stafford North Jn including Stone to Norton Bridge were closed for the final switch to the new flyover. Now in use by services from 29th March 2016. The question is would Stafford Station area and Norton Bridge area be updated so that it's possible to chain up with Rugby SCC North? I've taken a shot with permission off RailCam Signalling Diagrams to show what's been done I know it's not enough to do anything but I maybe able to get hold of other info. Post has attachments. Log in to view them. Aaron (AJRO) | Timetable Writer Last edited: 30/03/2016 at 11:19 by HST125Scorton Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 11:26 #81499 | |
Sacro
1171 posts |
Assuming there's no conflict of interest issues, then anything is possible. That diagram gives signal IDs, but there'd also be a need for track circuit lengths, any speed changes, signalling aspects and other technical data.
Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 11:40 #81500 | |
madaboutrains
316 posts |
The Scheme plan is full of Red meaning quite a lot of new track! Post has attachments. Log in to view them. RIP Feltham Panel 1 Log in to reply The following users said thank you: ajax103, Peter Bennet |
Stafford/Norton Bridge 30/03/2016 at 11:42 #81501 | |
Peter Bennet
5419 posts |
This link was posted elsewhere. Peter I identify as half man half biscuit - crumbs! Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 11:42 #81502 | |
madaboutrains
316 posts |
Stafford No4, Stafford No5, Norton Bridge workstation are now all at Rugby ROC! 4 peoples worth of work down to just one duty signaller!
RIP Feltham Panel 1 Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 11:45 #81503 | |
HST125Scorton
1198 posts |
I cannot read that image you posted madaboutrains. Could you blow it up a little so I can read it.
Aaron (AJRO) | Timetable Writer Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 11:46 #81504 | |
Peter Bennet
5419 posts |
" said:The Scheme plan is full of Red meaning quite a lot of new track!Do you have a better resolution version that which you could email to Geoff. Peter I identify as half man half biscuit - crumbs! Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 11:48 #81505 | |
HST125Scorton
1198 posts |
When updated if it goes ahead will the 2009 panel stay aswell as the new 2016 one? So when loading up you can choose 2009 or 2016. Aaron (AJRO) | Timetable Writer Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 11:54 #81506 | |
madaboutrains
316 posts |
Aron, 2009 is not a panel but a workstation. I think it was about 2002 the panel shut...
RIP Feltham Panel 1 Log in to reply The following user said thank you: HST125Scorton |
Stafford/Norton Bridge 30/03/2016 at 12:16 #81507 | |
madaboutrains
316 posts |
Peter Bennet wrote: Quote: Do you have a better resolution version that which you could email to Geoff.Whats Geoff's email please? RIP Feltham Panel 1 Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 16:02 #81516 | |
58050
2660 posts |
I e-mailed Geoff the sigannling notice for the re-signalling scheme at Norton bridge abput 2 months ago when I received it, so he already has it.
Log in to reply |
Stafford/Norton Bridge 30/03/2016 at 18:10 #81520 | |
JamesN
1611 posts |
" said:I e-mailed Geoff the sigannling notice for the re-signalling scheme at Norton bridge abput 2 months ago when I received it, so he already has it.This appears to be the red/green scheme plan, which is a lot more detailed than the yellow perils. Dan I suggest you get in touch with him via PM. Log in to reply |