Hi. A question from a light user. I am trying the Wembley Suburban sim and am having a problem with LU trains timetabled to use Harrow Siding. When I signal train into siding from Harrow P1 I get a "phone call" saying train is using freight lines and get penalised though I can force train into siding using option in phone call. Am I missing something ??? edit:- sim version is 2.1 loader 4.5.13 Last edited: 27/02/2017 at 20:34 by Grid56 Reason: add version no Log in to reply |
LU trains at Harrow 27/02/2017 at 21:22 #93387 | |
TUT
545 posts |
Grid56 in post 93386 said:Hi. A question from a light user.Yeah, it's a mistake in the timetable. I simply went ahead and fixed it myself by going to the Timetable menu and selecting Edit (F4). This brings up the Timetable List window. Then click on the Train Types tab, go to LU tube stock and click Edit. Then check "Can use freight lines" (bottom centre). Last edited: 27/02/2017 at 21:22 by TUT Reason: typo Log in to reply The following user said thank you: Grid56 |
LU trains at Harrow 04/03/2017 at 12:24 #93488 | |
Grid56
5 posts |
Thanks TUT Fix works perfectly. Much obliged. Log in to reply |