WORCESTER SIGNALBOXES 14/02/2011 at 13:42 #2434
postman
Avatar
47 posts
Can anyone explain why Henwick, Tunnel Junction & Station box don't have block instruments between them? They use block bells to offer trains etc.
Log in to reply
WORCESTER SIGNALBOXES 14/02/2011 at 13:42 #13657
postman
Avatar
47 posts
Can anyone explain why Henwick, Tunnel Junction & Station box don't have block instruments between them? They use block bells to offer trains etc.
Log in to reply
WORCESTER SIGNALBOXES 14/02/2011 at 16:05 #13667
Zoe
Avatar
252 posts
Both lines are bi-directional single lines and are worked by Track Circuit Block with acceptance levers.
Log in to reply
WORCESTER SIGNALBOXES 14/02/2011 at 18:16 #13673
postman
Avatar
47 posts
Hi Zoe. One thing I have noticed on inside pictures regarding Tunnel Junction is:
one of the lines is a reversable ( Down Line ) I believe, has a block instrument and exceptance lever too ?

Log in to reply
WORCESTER SIGNALBOXES 14/02/2011 at 18:33 #13675
Zoe
Avatar
252 posts
The lines I describe above were from Worcester Shrub Hill and Tunnel Junction to Henwick. From Tunnel Junction to Shrub Hill the bi-direcitonal "up and down main" line is TCB with acceptance levers but the down main is Absolute Block.