Issue with Cliffe Sidings (3010) GF bug 29/12/2022 at 09:58 #149765 | |
ajax103
1123 posts |
On the 2015 timetable starting at midnight, there is 0Y50 which enters once the shunter calls up and as the signaller you give permission to enter however... When you bring up the actual ground frame and you operate it correctly, for some unknown reason the tick boxes that state Permission to leave or enter Cliffe can't be used so the train just sits there and constantly rings up moaning they're awaiting the signal even though the route has been set for it to head towards Hoo Junction with no other train in the area and yes I've clicked on said boxes to enable them to be ticked but they do nothing. I've tried this on the Beginner and Leaf Fall difficulty setting so it's not just a one off but every time, in fact the only possible way to get a train off Cliffe Marine sidings and towards Hoo Junction is to tell the driver to pass signal CLF4 at danger which surely isn't the correct method. I've looked at the wiki and no matter what it says, the instructions simply don't work therefore I am of the firm belief that it is a bug which needs to be reported. How does anyone else manage with this? Log in to reply |
Issue with Cliffe Sidings (3010) GF bug 29/12/2022 at 10:26 #149767 | |
bill_gensheet
1432 posts |
Click frame F button Rclick frame N letter (pops up graphics) 1 rev 2 rev 3 rev 2 nor click permission to leave Instructions: The FPL is required to be placed normal to enable a train to enter or leave the siding complex. Post has attachments. Log in to view them. Log in to reply The following user said thank you: ajax103 |
Issue with Cliffe Sidings (3010) GF bug 29/12/2022 at 10:46 #149768 | |
ajax103
1123 posts |
bill_gensheet in post 149767 said:Click frame F buttonThank you that's finally done it however just curious because prior to doing what you explained to me, I told the driver to pass the signal at danger heading towards Cliffe Brett multiple times but the sim refused to process it - why is that? the route appeared to be set, the only thing I didn't do because I was struggling with it was the setting the FPL to normal as explained above. Log in to reply |
Issue with Cliffe Sidings (3010) GF 29/12/2022 at 12:19 #149771 | |
JamesN
1613 posts |
The train could see the ground frame wasn't set correctly and that it wasn't safe to proceed
Log in to reply The following user said thank you: ajax103 |
Issue with Cliffe Sidings (3010) GF 29/12/2022 at 12:32 #149773 | |
bill_gensheet
1432 posts |
The train will proceed when given PSAR with the FPL at R (= unlocked). May be more to it but can only replicate myself by leaving the points wrong. Log in to reply The following user said thank you: ajax103 |