Down Decoy Yard capacity 06/10/2024 at 15:44 #158766
bugsy
Avatar
1766 posts
I note that the scratchpad for the Down Decoy Yard has only has one train ID slot.
I assume that's because only one train can occupy the yard at any one time.
For some reason I thought that more than one train could be at that location.


Post has attachments. Log in to view them.
Everything that you make will be useful - providing it's made of chocolate.
Log in to reply
Down Decoy Yard capacity 06/10/2024 at 16:50 #158767
mfloyd
Avatar
189 posts
It has one for each line?
Ripley, Derbyshire
Log in to reply
The following user said thank you: bugsy
Down Decoy Yard capacity 07/10/2024 at 09:15 #158775
flabberdacks
Avatar
636 posts
Do you mean a four-digit 'train describer berth'? The train describer doesn't have any bearing on how many trains you can put onto a piece of track.
Log in to reply
Down Decoy Yard capacity 07/10/2024 at 13:40 #158778
vloris
Avatar
39 posts
As you said, it's just a scratchpad: the berth is not connected to anything.

The yard has a lot of capacity and is an entry/exit-point from the simulation point of view. Trains you send there exit the simulation, and new trains can enter there. I don't think SimSig is simulating any kind of limit on how many trains can be in there at any one time.

Log in to reply
Down Decoy Yard capacity 07/10/2024 at 15:32 #158779
clive
Avatar
2789 posts
vloris in post 158778 said:

The yard has a lot of capacity and is an entry/exit-point from the simulation point of view. Trains you send there exit the simulation, and new trains can enter there. I don't think SimSig is simulating any kind of limit on how many trains can be in there at any one time.
Actually, it does. Based on train length, nothing more detailed than that.

Log in to reply
The following user said thank you: vloris
Down Decoy Yard capacity 07/10/2024 at 16:02 #158781
bugsy
Avatar
1766 posts
Thanks for the replies which clarify things for me.

I did wonder about the one scratchpad berth but I didn't think that there could be only one train in there.
Plenty go in and plenty come out.

🙂

Everything that you make will be useful - providing it's made of chocolate.
Log in to reply
Down Decoy Yard capacity 07/10/2024 at 16:08 #158783
58050
Avatar
2659 posts
The 1988 Eastern Region Quail shows 11 dead Sdgs & a cripple Sdg in Down Decoy Yard. At that time was usually filled with MGR sets.
Log in to reply
Down Decoy Yard capacity 07/10/2024 at 16:29 #158784
jc92
Avatar
3685 posts
bugsy in post 158781 said:
Thanks for the replies which clarify things for me.

I did wonder about the one scratchpad berth but I didn't think that there could be only one train in there.
Plenty go in and plenty come out.

🙂
I normally use that scratchpad berth to either permanently put the pilots headcode in for reference, or if a train enters from the yard and I need to detain it, but make a note of whats waiting.

"We don't stop camborne wednesdays"
Log in to reply