Rules used in the Project X timetable somehow don't work

You are here: Home > Forum > Simulations > Released > North Wales Coast > Rules used in the Project X timetable somehow don't work

Page 1 of 1

Rules used in the Project X timetable somehow don't work 02/11/2013 at 17:47 #50555
Finger
Avatar
220 posts
It seems there are some problems with the rule "X must not depart before Y finished dividing". As you can see from the screenshot, 7F14 has finished dividing (the DEF activity), but 0S041 is still blocked by that rule.
Post has attachments. Log in to view them.
Log in to reply
Rules used in the Project X timetable somehow don't work 02/11/2013 at 17:53 #50558
headshot119
Avatar
4869 posts
The best bet for you is to abandon the rule. It's a known issue with the TT and will be fixed when the sim is re-released with an updated TT. (Unfortunately due to a couple of reasons we can't release the TT before the new sim)
"Passengers for New Lane, should be seated in the rear coach of the train " - Opinions are my own and not those of my employer
Log in to reply
The following users said thank you: Hawk777, Finger
Rules used in the Project X timetable somehow don't work 03/11/2013 at 07:15 #50572
Hawk777
Avatar
386 posts
Was facing this myself! I’ll just abandon the rules. Side note, I’ve also seen a few trains in this timetable claim they’ve been wrong-routed when they haven’t (e.g. into the run-round line at Holyhead).
Log in to reply
Rules used in the Project X timetable somehow don't work 03/11/2013 at 12:30 #50575
Finger
Avatar
220 posts
So true, I've come across the RRL at Holyhead problem, too. However, I discovered the trains won't work even if I force them to the RRL (they won't properly arrive and detach the loco) so I use a spare platform (3, but maybe 1 is possible too) when I have one.
Log in to reply
Rules used in the Project X timetable somehow don't work 06/11/2013 at 07:07 #50753
Hawk777
Avatar
386 posts
They won’t do any more actions if you cancel the timetable. I just cancel the timetable, wait a few seconds for the train to start rolling, and then reinstate the timetable in the F2 list with the RRL as next location. Once the train has passed the signal, it’s happy to go into the RRL and do its stuff.
Log in to reply