Running Round Trains at Northallerton - Y694 GPL Signal Will Not Clear

You are here: Home > Forum > Simulations > Released > York North/South > Running Round Trains at Northallerton - Y694 GPL Signal Will Not Clear

Page 1 of 1

Running Round Trains at Northallerton - Y694 GPL Signal Will Not Clear 21/07/2017 at 12:52 #96523
Phil-jmw
Avatar
675 posts
Running the Summer 1991 TT on Monday, at approximately 0315 engineers train 7P01 Tees Yd - Tees Yd arrives at Northallerton from Darlington to run round then proceed back to Tees Yd via Eaglescliffe. 0P01 detaches, reverses behind Y691 GPL signal on the Up Main, before proceeding to the Dn Eaglescliffe to reverse behind Y694 GPL to then set back onto its train in the Up Main platform. However, with a route set Y694 - Y474, Y694 GPL does not clear. I had to talk the loco past the signal to set back onto its train.

Unfortunately I didn't save the sim at that time but 7P02 has just performed the same move so I've attached a save. Has anyone else encountered this?


Regards,

Phil.

Post has attachments. Log in to view them.
Last edited: 21/07/2017 at 13:10 by Phil-jmw
Reason: None given

Log in to reply
Running Round Trains at Northallerton - Y694 GPL Signal Will Not Clear 21/07/2017 at 19:43 #96532
Stephen Fulcher
Avatar
2078 posts
From playing around with the sim a little, it looks like the platform is not simulated to be permissive.

Logged on Mantis 17662

Log in to reply
Running Round Trains at Northallerton - Y694 GPL Signal Will Not Clear 22/07/2017 at 11:09 #96545
Phil-jmw
Avatar
675 posts
Ok thanks Stephen.
Log in to reply