Road setting in Newhaven Harbour and Berwick 06/05/2023 at 17:55 #151701 | |
SpDrS420
4 posts |
Hi, I bought East Coastway yesterday. Now I fail at the problem that I can not set a road in Newhavon Harbour from Seaford direction. The two level crossings are closed and at the left one the "Release" indicator lights up. Nevertheless, I get the message that the route is not available. Until now I have handled it by calling the trains to let them pass the signal verbally. But that can't be common practice. So how can I set up this route? Thanks for an answer, and sorry if the question has been explained before. However, I have not found such a thread. Many greetings from Germany Last edited: 06/05/2023 at 19:26 by SpDrS420 Reason: None given Log in to reply |
Road setting in Newhaven Harbour and Berwick 06/05/2023 at 18:20 #151702 | |
Steamer
3997 posts |
Which signals specifically are you attempting to set a route between? Are you attempting to set a route from CCO29 to CCO30 while CCO30 is already cleared? This might cause the message as these routes have to be set sequentially. "Don't stress/ relax/ let life roll off your backs./ Except for death and paying taxes/ everything in life.../ is only for now." (Avenue Q) Log in to reply The following user said thank you: SpDrS420 |
Road setting in Newhaven Harbour and Berwick 06/05/2023 at 19:07 #151703 | |
TUT
545 posts |
At least in the case of NH40 it can't be cleared until a train is on the approach. Quote from the manual: Quote: There are a couple of realistic interlocking 'quirks' at the Harbour which are reproduced in the simulation and may catch both the wary and unwary alike. Firstly the point detection on NH18 points are part of the control circuits for NH42 and NH102 signals. Secondly the berth track is required occupied before NH40 lever is released. Log in to reply The following user said thank you: SpDrS420 |
Road setting in Newhaven Harbour and Berwick 06/05/2023 at 19:24 #151704 | |
SpDrS420
4 posts |
Steamer in post 151702 said:Which signals specifically are you attempting to set a route between?I'm concerned with signal NH40, I can cope with journeys from Lewes to Seaford, in the opposite direction I don't know what to do. TUT in post 151703 said: At least in the case of NH40 it can't be cleared until a train is on the approach. Quote from the manual:Yes, I have already read that in the manual/wiki. But I don't understand what I have to do to run in a route. The track in front of signal NH 40 is already occupied, but a route cannot be set. Maybe I'll just describe how I proceed, then you can see if I'm doing something wrong: The train is in Seaford, I set the route from signal NH42 by left clicking on it. The train moves in the direction of signal NH40. I close both level crossings and activate the "Release" indicator. Until then I have not operated the block modules to Newhaven Town or allowed the exit from Newhaven Harbour. However, the route from signal NH40 to track 2 at Newhaven Harbour is rejected with the comment "Route not available". Log in to reply |
Road setting in Newhaven Harbour and Berwick 06/05/2023 at 19:39 #151705 | |
postal
5269 posts |
To make sure that everyone is working from the same information, can you supply a saved game with the problem?
“In life, there is always someone out there, who won’t like you, for whatever reason, don’t let the insecurities in their lives affect yours.” – Rashida Rowe Log in to reply The following user said thank you: SpDrS420 |
Road setting in Newhaven Harbour and Berwick 06/05/2023 at 19:48 #151706 | |
SpDrS420
4 posts |
Ok, I have now got the route set. I think that was actually because I have otherwise already pulled the exit from Newhaven Harbour. Thanks a lot for the help Log in to reply |