Some Issues v5.6 Post 2006 era 17/08/2023 at 20:56 #152881
Soton_Speed
Avatar
285 posts
1. Loco hauled trains on the Exmouth branch don't appear to obey the appropriate Speed differential - see 3s12_spd_diff.ssg

2. Should trains tt'd to rev behind E35, call wrong route if routed onto the Dn Main as they head off towards Dawlish otherwise?

3. What is the reason for not being able to route from P1(E160) and P3(E260) towards the E35LoS?

4. Trains talked passed CN12 don't appear operate the 'OTW'/collect the token (in reality) between Crediton and Eggsford? See 2B84.ssg

TIA.

Post has attachments. Log in to view them.
In Zone 6, no one can hear you scream...
Log in to reply
Some Issues v5.6 Post 2006 era 17/08/2023 at 22:21 #152884
Peter Bennet
Avatar
5402 posts
Online
Soton_Speed in post 152881 said:
1. Loco hauled trains on the Exmouth branch don't appear to obey the appropriate Speed differential - see 3s12_spd_diff.ssg

It's not coded to do that but I can look into it.

Quote:

2. Should trains tt'd to rev behind E35, call wrong route if routed onto the Dn Main as they head off towards Dawlish otherwise?

Looks like it.

Quote:

3. What is the reason for not being able to route from P1(E160) and P3(E260) towards the E35LoS?

That's what the tables tell me.

Quote:

4. Trains talked passed CN12 don't appear operate the 'OTW'/collect the token (in reality) between Crediton and Eggsford? See 2B84.ssg
TIA.

The whole Barnstaple branch needs rebuilt but I don't have the information for it.

I do have a new version pending but I've been waiting for someone to check something (which I'd forgotten about).

Peter

I identify as half man half biscuit - crumbs!
Log in to reply
The following user said thank you: sunocske
Some Issues v5.6 Post 2006 era 19/08/2023 at 18:10 #152905
headshot119
Avatar
4869 posts
Soton_Speed in post 152881 said:
1. Loco hauled trains on the Exmouth branch don't appear to obey the appropriate Speed differential - see 3s12_spd_diff.ssg
Mantis 39194 - Though the simulation could well predate differential speeds being the norm.

Soton_Speed in post 152881 said:
2. Should trains tt'd to rev behind E35, call wrong route if routed onto the Dn Main as they head off towards Dawlish otherwise?
Mantis 39195

Soton_Speed in post 152881 said:
3. What is the reason for not being able to route from P1(E160) and P3(E260) towards the E35LoS?
No routes exist in the interlocking.

Soton_Speed in post 152881 said:
4. Trains talked passed CN12 don't appear operate the 'OTW'/collect the token (in reality) between Crediton and Eggsford? See 2B84.ssg

TIA.
Mantis 39196

"Passengers for New Lane, should be seated in the rear coach of the train " - Opinions are my own and not those of my employer