Upcoming Games

(UTC times)


Full list
Add a game

Upcoming Events

No events to display

Crewe PSB Late May Bank Holiday 2024

You are here: Home > Forum > Simulations > Timetables > Crewe > Crewe PSB Late May Bank Holiday 2024

Page 1 of 1

Crewe PSB Late May Bank Holiday 2024 01/09/2024 at 12:39 #158380
HST125Scorton
Avatar
1192 posts
Timetable now available via the User Content on the Loader and via the Uploaded Files.
Any issues please report below.

Friday 24th May:
Final normal working day before engineering works start taking place along the WCML.

Saturday 25th May:
Bank Holiday Engineering works are taking place along the WCML. Crewe to Stafford Mainlines are closed. Diversions are taking place via Barthomley Junction. Also Crewe to Shrewsbury is also closed for engineering works with diversions via Chester. Basford Hall Yard & Salop Goods Junction is also closed from just after midnight on Saturday morning.

Aaron (AJRO) | Timetable Writer
Last edited: 01/09/2024 at 13:01 by HST125Scorton
Reason: None given

Log in to reply
Crewe PSB Late May Bank Holiday 2024 07/09/2024 at 06:36 #158441
BenWright
Avatar
195 posts
Enjoying the timetable so far but have noticed that 1D10 and 1K03 have platform clashes
Log in to reply
Crewe PSB Late May Bank Holiday 2024 07/09/2024 at 10:23 #158447
HST125Scorton
Avatar
1192 posts
1K03 > 1D51 moved to Platform 10 as booked. Totally over looked that while testing.
Aaron (AJRO) | Timetable Writer
Log in to reply
The following user said thank you: BenWright
Crewe PSB Late May Bank Holiday 2024 07/09/2024 at 17:48 #158450
BenWright
Avatar
195 posts
No worries, thank you
Log in to reply
Crewe PSB Late May Bank Holiday 2024 08/09/2024 at 04:14 #158454
BenWright
Avatar
195 posts
Another note as well 1W11 has no timing for Crewe Sydney Bridge

EDIT: Realised that's because there is no timing for Crewe Sydney Bridge!

Last edited: 08/09/2024 at 07:25 by BenWright
Reason: None given

Log in to reply
Crewe PSB Late May Bank Holiday 2024 08/09/2024 at 12:05 #158461
HST125Scorton
Avatar
1192 posts
Crewe Sydney Bridge Timing point was removed roughly when Crewe Simulation came out. So this location is using pass ticks without times.

Next version of Crewe should remove the requirement to have it without affecting the provided timetables that came with the simulation.
[40691] Investigate future TT compatibility

Aaron (AJRO) | Timetable Writer
Log in to reply
Crewe PSB Late May Bank Holiday 2024 13/09/2024 at 17:09 #158509
Robyn
Avatar
74 posts
For all persons wondering what happened to Sydney Br, it was replaced/renamed to Crewe Signal CE154 on the UP and removed entirely on the DN.

For DN trains use the dep time at Crewe station +3 mins to get Sydney Br

7-5-5, closing of comment
Log in to reply
The following user said thank you: HST125Scorton