2Q08 14/04/2017 at 08:04 #94479 | |
Giantray
347 posts |
2Q08 comes from Radyr and reverses at Ninian Park according to the timetable. It stops in the platform to reverse back via the Leckwith Branch to Bridgend. However there is no signalled move from the platform onto the Leckwith Branch. The driver rings in wanting authority to move. Is this usual practice to do a timetabled "unsignalled" move? If it is then this should not happen in rhe real world. If there is no signalled move, the train should be reversed at a location where it can be signalled to do such a move, where it gains security of the interlocking to do the move and not rely on the Signaller to set up a route and protect the move each time.
Professionalism mean nothing around a bunch of Amateur wannabees! Log in to reply |
2Q08 14/04/2017 at 09:28 #94480 | |
postal
5264 posts |
Giantray in post 94479 said:2Q08 comes from Radyr and reverses at Ninian Park according to the timetable. It stops in the platform to reverse back via the Leckwith Branch to Bridgend. However there is no signalled move from the platform onto the Leckwith Branch. The driver rings in wanting authority to move. Is this usual practice to do a timetabled "unsignalled" move? If it is then this should not happen in rhe real world. If there is no signalled move, the train should be reversed at a location where it can be signalled to do such a move, where it gains security of the interlocking to do the move and not rely on the Signaller to set up a route and protect the move each time.Don't know whether it is the same problem but 2Q08 was last discussed here. “In life, there is always someone out there, who won’t like you, for whatever reason, don’t let the insecurities in their lives affect yours.” – Rashida Rowe Last edited: 14/04/2017 at 09:30 by postal Reason: None given Log in to reply |
2Q08 14/04/2017 at 10:44 #94481 | |
JamesN
1608 posts |
postal in post 94480 said:Different Issue Entirely. Giantray in post 94479 said: 2Q08 comes from Radyr and reverses at Ninian Park according to the timetable. It stops in the platform to reverse back via the Leckwith Branch to Bridgend. However there is no signalled move from the platform onto the Leckwith Branch. The driver rings in wanting authority to move. Is this usual practice to do a timetabled "unsignalled" move? If it is then this should not happen in rhe real world. If there is no signalled move, the train should be reversed at a location where it can be signalled to do such a move, where it gains security of the interlocking to do the move and not rely on the Signaller to set up a route and protect the move each time.There was some resignalling work at Ninian Park a couple of years ago; one of the first phases of migrating control from Cardiff Panel to South Wales ROC. As such, the sim isn't quite an accurate match for the timetable period. There are now Main Aspect signals at both ends of both platforms at Ninian Park, which weren't there in the days Cardiff Panel controlled Ninian Park. Suggested TT fix; as I agree with your sentiment that a manually set route seems very unlikely. Suggested timetable fix would see 2Q08 reverse behind C320 on the Treforest Single. Last edited: 14/04/2017 at 10:51 by JamesN Reason: None given Log in to reply The following users said thank you: postal, Giantray |
2Q08 14/04/2017 at 15:13 #94486 | |
Giantray
347 posts |
Thank You JamesN, that explains it. I have already done what you have said about re-timetabling the train.
Professionalism mean nothing around a bunch of Amateur wannabees! Last edited: 14/04/2017 at 15:13 by Giantray Reason: None given Log in to reply |